Allocate File to Officer | Yes | 14/02/2020 | 21/02/2020 |
Produce Assessment Checklist | Yes | 21/02/2020 | 03/03/2020 |
Information Complies? | No | 03/03/2020 | 05/03/2020 |
Internal Referrals? | No | 03/03/2020 | 03/03/2020 |
Determination of Construction Certificate | Approved | 05/03/2020 | 25/03/2020 |
Information Required | Yes | 05/03/2020 | 05/03/2020 |
Produce Additional Information Letter | Yes | 05/03/2020 | 05/03/2020 |
Information received | Satisfactory | 05/03/2020 | 25/03/2020 |
Are Fire Safety Measures Required? | Yes | 25/03/2020 | 26/03/2020 |
CC Plans & Documents Signed/Stamped | Yes | 25/03/2020 | 25/03/2020 |
Construction Certificate Released | Picked up at Council | 25/03/2020 | 27/03/2020 |
Select Type of Inspections For CSI Letter | Yes | 25/03/2020 | 25/03/2020 |
Produce Critical Stage Inspection Letter | Yes | 25/03/2020 | 25/03/2020 |
Notice of Commencement Received? | Yes | 26/03/2020 | 26/03/2020 |
PCA Agreement Form | Yes | 26/03/2020 | 26/03/2020 |
Create Fire Safety Schedule Letter | Yes | 26/03/2020 | 26/03/2020 |