Allocate File to Officer | Yes | 22/05/2020 | 02/06/2020 |
Produce Assessment Checklist | Yes | 02/06/2020 | 16/06/2020 |
Information Complies? | Yes | 16/06/2020 | 16/06/2020 |
Internal Referrals? | No | 16/06/2020 | 16/06/2020 |
Update DA Consent Approval Date and Plan Details | Yes | 16/06/2020 | 16/06/2020 |
Determination of Construction Certificate | Approved | 16/06/2020 | 16/06/2020 |
CC Plans & Documents Signed/Stamped | Yes | 18/06/2020 | 18/06/2020 |
Construction Certificate Released | Sent Through the Post | 18/06/2020 | 18/06/2020 |
Select Type of Inspections For CSI Letter | Yes | 16/06/2020 | 16/06/2020 |
Produce Critical Stage Inspection Letter | Yes | 16/06/2020 | 16/06/2020 |
Update No. of Inspections Custom Field | Yes | 16/06/2020 | 18/06/2020 |
Produce outstanding fees letter | Yes | 18/06/2020 | 18/06/2020 |
Inspection Fees Paid? | Yes | 18/06/2020 | 27/08/2020 |
Notice of Commencement Received? | Yes | 03/07/2020 | 03/07/2020 |
PCA Agreement Form | Yes | 27/08/2020 | 27/08/2020 |
Critical Stage Inspection | Fencing Inspection Type | 27/08/2020 | 27/08/2020 |
PCA Sign Erected | Yes | 27/08/2020 | 27/08/2020 |
Sediment/Crossing/Tree Inspection Result | Satisfactory | 27/08/2020 | 27/08/2020 |
Footings Inspection Result | Satisfactory | 27/08/2020 | 27/08/2020 |
Final Inspection Result - Fences & Signage | Satisfactory | 27/08/2020 | 29/04/2021 |