Allocate File to Officer | Yes | 09/09/2020 | 14/09/2020 |
Produce Assessment Checklist | Yes | 14/09/2020 | 10/11/2020 |
Information Complies? | No | 10/11/2020 | 10/11/2020 |
Internal Referrals? | No | 30/03/2022 | 30/03/2022 |
Update DA Consent Approval Date and Plan Details | Yes | 30/03/2022 | 30/03/2022 |
Determination of Construction Certificate | Approved | 05/04/2022 | 05/04/2022 |
Information Required | Yes | 10/11/2020 | 10/11/2020 |
Produce Additional Information Letter | Yes | 10/11/2020 | 10/11/2020 |
Information received | Satisfactory | 10/11/2020 | 30/03/2022 |
Are Fire Safety Measures Required? | No | 05/04/2022 | 05/04/2022 |
CC Plans & Documents Signed/Stamped | Yes | 05/04/2022 | 06/04/2022 |
Construction Certificate Released | Delivered | 06/04/2022 | 06/04/2022 |
Select Type of Inspections For CSI Letter | Yes | 05/04/2022 | 05/04/2022 |
Produce Critical Stage Inspection Letter | Yes | 05/04/2022 | 05/04/2022 |
Update No. of Inspections Custom Field | Yes | 05/04/2022 | 06/04/2022 |
Notice of Commencement Received? | Yes | 05/05/2022 | 05/05/2022 |
PCA Agreement Form | Yes | 06/04/2022 | 06/04/2022 |
Critical Stage Inspection | Commercial Inspection Type | 06/04/2022 | 08/06/2023 |
Are Fire Safety Measures Required? | No | 05/04/2022 | 05/04/2022 |
PCA Sign Erected | Yes | 08/06/2023 | 08/06/2023 |