Allocate File to Officer | Yes | 17/09/2020 | 24/09/2020 |
Information Complies? | No | 20/10/2020 | 20/10/2020 |
Internal Referrals? | No | 03/11/2020 | 03/11/2020 |
Update DA Consent Approval Date and Plan Details | Yes | 03/11/2020 | 03/11/2020 |
Determination of Construction Certificate | Approved | 03/11/2020 | 03/11/2020 |
Information Required | Yes | 20/10/2020 | 20/10/2020 |
Produce Additional Information Letter | Yes | 20/10/2020 | 20/10/2020 |
Information received | Satisfactory | 20/10/2020 | 03/11/2020 |
Are Fire Safety Measures Required? | No | 03/11/2020 | 03/11/2020 |
CC Plans & Documents Signed/Stamped | Yes | 03/11/2020 | 03/11/2020 |
Construction Certificate Released | Sent Through the Post | 03/11/2020 | 03/11/2020 |
Select Type of Inspections For CSI Letter | Yes | 03/11/2020 | 03/11/2020 |
Produce Critical Stage Inspection Letter | Yes | 03/11/2020 | 03/11/2020 |
Notice of Commencement Received? | Yes | 21/06/2022 | 21/06/2022 |
PCA Agreement Form | Yes | 20/07/2022 | 20/07/2022 |
Critical Stage Inspection | Carport/Garage Inspection Type | 19/07/2022 | 19/07/2022 |
PCA Sign Erected | Yes | 19/07/2022 | 20/07/2022 |
Footings Inspection Result | Unsatisfactory | 19/07/2022 | 19/07/2022 |
Slab Inspection Result | Satisfactory | 09/08/2022 | 09/08/2022 |
Footings Inspection Result | Satisfactory | 09/08/2022 | 09/08/2022 |